Penambahan PJU di Jakut Terkendala Lelang

Street Lights Addition in North Jakarta Hampered by Auction

Tuti Kurnia, North Jakarta head Sub-dept. of Industry and Energy, ensured that the public light installation in her area or at six sub-districts is not meet the target. There are six auction packages canceled by local Goods and Service Procurement Units (UPBBJ).

Our target was installing 7,315 public lights, but we only installed 6,600

"Our target was installing 7,315 public lights, but we only installed 6,600," she said, Wednesday (11/4).

The six canceled packages are Tanjung Priok I, Tanjung Priok II, Koja I, Koja II, Kelapa Gading I, and Penjaringan I. These packages total budget is Rp 3 billion.

25 Street Lights on Jalan Raya Bekasi Fixed

"We'll still run the maintenance for the existing spotlight," she added.

Meanwhile, Muhammad Chamdan, North Jakarta Head of UPPBJ, admitted that the packages must be eliminated due to no more time for installation.

"The installation needs 60 days," he stated.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2633 personNurito
  2. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2355 personTiyo Surya Sakti
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye976 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye839 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye734 personBudhi Firmansyah Surapati